Napoleon City Council Monday night gave initial approval to a contractor for the new pool project, and officials remain positive the project will stay on schedule.

During its last meeting, council rejected all bids for the project which included a new pool facility and features, as well as a new bathhouse and clubhouse building, because the bids were over the 10% allowed.

Council Monday night approved first reading of a resolution to enter into a contract for just the pool facility portion of the project. The building will be re-bid at a later date.

City Manager Joel Mazur said he was only requesting first reading Monday night because there are still some pricing issues that need to be worked out, but he hoped to have those clarified when council meets again in two weeks.

The building will be smaller, including a smaller deck size and fewer restrooms, but Mazur said the priority has been on the pool.

“We were able to work in all the alternates that we wanted to, the only thing we omitted from this contract was the rock climbing wall, and that could be added in later if everything comes in under budget,” Mazur said.

The facility is expected to include two large slides, a children’s slide, an eight-lane competition pool, splash features and shade structures.

“It’s a pool project before it’s a bathhouse and clubhouse project,” Mazur said. “We need to make sure it’s a state-of-the-art-facility. People are going to come there to swim and play in the pool, not visit the bathhouse and clubhouse.”

He added both those buildings will, however, be upgrades from what was there before.

Last year, Napoleon voters approved a new 1.9 mills property tax levy to fund construction of a new pool facility.

The levy will last 20 years and adds an estimated $67 to the annual property tax bill of a $100,000 home. It will generate $5.2 million, though the new pool construction is expected to be capped at $3.9 million. The remainder would help pay on the debt of the project, as well as set up a maintenance fund.

Though the original timeline had construction starting this summer, officials believe the delay will not change the target opening of Memorial Day.

City Public Works Director Chad Lulfs said the contractor could begin construction in September or October and he expects the timeline to remain.

“We do have time to meet that schedule still,” Lulfs said.

He added the design drawings for the pool have been completed, but the modified drawings for the building are still being worked on after the changes were made.

In other business, council:

Passed, under suspension of the rules requiring three readings, ordinances dealing with transfers and appropriations.

Passed third and final readings to amend certain sections of the water and sewer rules and to enter into a grant agreement with the Department of Homeland Security. Both pieces of legislation also had emergency clauses.

Approved a bid of $79,000 for concrete crushing, though the budgeted amount of $100,000 likely will be spent. The city uses the concrete in project and currently is out, causing it to pay upwards of twice the price of crushing to purchase stone.

Approved a bid of $512,000 for improvements to a waterline on Glenwood Avenue. The estimate had been $510,000.

Accepted a $500 grant for school threat assessment training for the school resource officer.

Email comments to briank@northwestsignal.net

I started at the Northwest Signal in 1994 and became editor in 2004. I graduated from Bowling Green State University in 1994.

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.